Are late penalties provided for?

The short answer

The law regulates penalties in both directions, but not in the same way. If you pay late, the penalty provided for in the contract cannot exceed 1% per month. If the developer delivers late, the law sets no automatic penalty: it exists only if the deed provides for it, and a lump-sum compensation on cancellation cannot exceed 10% of the price.

In detail

If the buyer pays late

For an off-plan sale, article 1601-30 of the Mauritian Civil Code provides that, if the contract provides for a penalty for late payments or instalments, its rate cannot exceed 1% per month. The text sets a cap, not an automatic penalty: a penalty is due only if the contract provides for it. The developer also cannot ask you to pay in advance of the stage payments: any payment before signing is prohibited (art. 1601-8), and the calls for funds follow capped construction stages.

If the contract contains a clause of automatic cancellation for non-payment, it takes effect only one month after a formal demand or an order to pay has gone unanswered. More time can be requested during that month, and the clause is deemed never to have applied if the debtor pays in the conditions set by the Judge in Chambers (art. 1601-10).

If the developer delivers late

The law sets no penalty that the developer must pay automatically. If the seller does not deliver within the agreed time and the delay is solely the seller's doing, you may choose between cancelling the sale and being put into possession (art. 1610), and the seller must be ordered to pay damages if you suffer loss as a result (art. 1611). It is then for the buyer to prove the loss, unless the contract provides for compensation.

The 10% cap on cancellation

Article 1601-11 prohibits the contract from stipulating a lump-sum compensation on cancellation above 10% of the price, payable by the party to whom the cancellation is attributable. The parties remain free to claim compensation for the loss actually suffered. Any clause contrary to articles 1601-7 to 1601-11, 1642-1 and 1646-1 is deemed unwritten (art. 1601-12).

What to have written into the contract

  • the delivery deadline, with a precise date;
  • the penalty payable by the developer in case of delay, its starting point, its method of calculation and any cap;
  • the rate of the penalty payable by the buyer, which cannot exceed 1% per month;
  • the amount of the compensation on cancellation, within the limit of 10% of the price.

Compare the two columns: a late-payment penalty that the buyer bears with no equivalent for the developer deserves discussion before signing. Your notary can advise you on the balance of the contract.

How we support you

On a new-build programme, we help you understand the payment schedule, the deadline clause and the penalties before signing, then we coordinate with the developer and the notary until the deed. We then follow your file with the developer until delivery.

2 official texts cited

Official sources

  1. Code Civil Mauricien (RGD edition, December 2025) — text in FrenchRegistrar-General's Department
  2. Code Civil Mauricien (in French)Government of Mauritius — Revised Laws of Mauritius (Attorney-General's Office), consolidation published by the Registrar-General's Department

Related questions