Property & investment · Buying off-plan (VEFA)
What happens if delivery is late?
The short answer
The deed must set a delivery deadline. If the seller does not deliver within the agreed time and the delay is solely the seller's doing, you may choose between cancelling the sale and being put into possession (art. 1610 of the Civil Code). The seller must also be ordered to pay damages if you suffer loss as a result (art. 1611).
In detail
The deadline is written in the deed
For an off-plan (VEFA) sale, the notarial deed must state the delivery deadline (art. 1601-7). It is the reference date for all your remedies: without a precise date, it becomes difficult to prove that there is a delay. The building is deemed complete when the works have been carried out and the equipment essential to its use has been installed; minor defects do not prevent completion (art. 1601-13).
Your two legal remedies
Article 1610 applies if the seller fails to deliver within the agreed time and the delay is solely the seller's doing. You then choose between:
- cancellation of the sale;
- being put into possession, that is, performance of the contract.
Article 1611 adds that, in all cases, the seller must be ordered to pay damages if the buyer suffers loss from the failure to deliver by the agreed date. The loss must be proven: rent paid while waiting, storage or rehousing costs, for example. The condition that the delay is solely the seller's doing matters: a delay with a shared or external cause is open to dispute.
No automatic penalty
The law sets no penalty that applies automatically to a late developer. A late-delivery penalty exists only if the contract provides for it. Have it written next to the delivery date, with its starting point, its calculation and any cap. Without a clause, you will have to prove your loss.
The cap on compensation on cancellation
On cancellation, the contract cannot set a lump-sum compensation above 10% of the price, but each party remains free to claim compensation for the loss actually suffered (art. 1601-11). Any clause to the contrary is deemed unwritten (art. 1601-12).
What the completion guarantee does not cover
The completion guarantee protects against the building not being finished, not against delay: delay is governed by the deed and articles 1610 and 1611.
What to do in practice
Keep in writing the dates announced, your exchanges with the developer and the supporting documents for your costs. Before making a claim, re-read the deadline clause and those on cancellation and penalties; a notary or a lawyer can tell you which remedy best suits your situation.
How we support you
Before signing, we help you read the deadline clause and spot what needs to be clarified. After the deed, we follow your file with the developer until delivery.
3 official texts cited
Official sources
- Code Civil Mauricien (RGD edition, December 2025) — text in FrenchRegistrar-General's Department
- Code Civil Mauricien (in French)Government of Mauritius — Revised Laws of Mauritius (Attorney-General's Office), consolidation published by the Registrar-General's Department
- Code Civil Mauricien (édition RGD 12/2025)Registrar-General's Department