Property & investment · Buying off-plan (VEFA)

What is the legal schedule of stage payments?

The short answer

The law does not set a single timetable: it caps the cumulative sums the developer may ask of you, namely 35% of the price at completion of the foundations, 70% when the building is watertight and 95% at completion of the building (art. 1601-30 of the Civil Code). The balance is payable when the unit is made available to you, and the amounts of each call are set in your deed.

In detail

The caps set by article 1601-30

For an off-plan sale (VEFA), article 1601-30 of the Mauritian Civil Code limits the total of payments or deposits. These are cumulative caps, read by adding up the calls for funds already paid:

  • 35% of the price at most at completion of the foundations;
  • 70% at most when the building is watertight;
  • 95% at most at completion of the building;
  • the balance when the unit is made available to you, with the possibility of consigning it in the event of a dispute over conformity with the contract.

Within these limits, the sums fall due either through constant periodic payments, or through successive payments whose amount depends on the progress of the works. If the sale is concluded under a condition precedent, no payment may be made until the condition is met. Completion of the foundations must be certified by a qualified professional (art. 1601-27).

An example of how to read it

The EDB guidelines for IRS, RES or PDS buyers describe the following schedule, called progressively as the works advance: 25% at signing of the deed, 10% at completion of the foundations, 35% when the building is watertight, 25% at completion and 5% when the premises are made available. Cumulatively, these calls give 25%, 35%, 70%, 95% then 100%: they respect the legal caps. For a property at Rs 10 million, this represents Rs 2.5 million at the deed, Rs 1 million at the foundations, Rs 3.5 million at watertight stage, Rs 2.5 million at completion and Rs 500,000 at handover of keys. This calculation illustrates the method; your percentages are those of your contract.

Before the deed: reservation and deposit

The seller may demand or accept nothing before signing (art. 1601-8). Only the security deposit of the preliminary contract is allowed: it is paid into a special account opened in your name, at a bank or with a notary, and may not exceed 25% of the forecast price if the period for completing the sale does not exceed one year, nor 2% if it does not exceed two years; no deposit may be demanded beyond that (art. 1601-42 and 1601-43).

Special cases

  • Detached house: for the completion guarantee to rest on the conditions of the operation, the foundations must be completed and payments may not exceed 20% of the price at the foundations, 45% when watertight and 85% at completion (art. 1601-32).
  • Late-payment penalty: if the contract provides one for your late payments, its rate may not exceed 1% per month.

Common pitfalls

A schedule that exceeds a cap, or in which a cumulative percentage goes down from one stage to the next, must be flagged before signing. A call for funds must also correspond to a stage actually reached: ask for the qualified professional's certificate for the foundations. Finally, deed costs (registration duty, notary fees, EDB file) are paid in addition to the call of the day.

How we support you

On a new-build programme, we help you understand the schedule proposed by the developer, step by step, and compare it with what the law allows. We check the programme's purchase framework, we coordinate with the developer and the notary through to the deed, then we follow your file with the developer through to delivery.

3 official texts cited

Official sources

  1. Code Civil Mauricien (in French)Government of Mauritius — Revised Laws of Mauritius (Attorney-General's Office), consolidation published by the Registrar-General's Department
  2. Guidelines for Buyers of Residential Property under the IRS / RES / PDS (Jan. 2025)Economic Development Board Mauritius
  3. Code Civil Mauricien (édition RGD 12/2025)Registrar-General's Department

Related questions