Checking a Developer in Mauritius

Programme approval, permits, completion guarantee, company accounts, delivery record: the checks to make before a reservation.

A new programme is judged on its documents. This guide tells you where to find each one, how to read it, which clauses of the reservation contract protect the buyer and which warning signs should make you step back.

Guide updated on 9 November 202614 min readBy Franck Penarrubia, head of the Westimmo agency

Check the programme,
not the reputation

Key points

The essentials at a glance, backed by the legal texts.

The EDB authorises an operation, not a brand: approval is checked programme by programme

In an off-plan sale, the deed must provide for a completion or refund guarantee, on pain of nullity (Civil Code, art. 1601-7)

No payment before the deed, apart from the reservation deposit placed in a special account (arts 1601-8 and 1601-38)

Developers and land promoters: registration with the REAA, phase 1 opened on 1 August 2026

01 The method

Why check the programme before the company

One group can carry several operations, each in its own company, with its own land, permit and financing.

One programme, one company, one file

A new programme rests on land, a permit, an EDB authorisation for sales to non-citizens and a company that sells. These four elements are checked one by one. A glossy brochure replaces none of them.

Reputation cannot be read in a ranking

A league table of developers mixes opinions, memories and interests. A document, on the other hand, can be checked: a permit has a number, an authorisation has a date, a deed has content imposed by law.

The buyer has written rights

The Mauritian Civil Code governs sales of property to be completed (off-plan sales) in articles 1601-1 to 1601-45. What the developer may ask for, when, and what it must hand over do not depend on its goodwill.

The right time is before the reservation

Once the deposit is paid, your room for manoeuvre shrinks. The checks in this guide take a few days and are done before you sign the preliminary contract.

02 The checks

Six checks, and where to make them

Each line points to a document the seller can give you or to a register you can search.

Cross-reading of the texts cited and of the EDB guidelines for the acquisition of residential property by non-citizens, re-read on 9 November 2026.
CheckWhat you ask forWhereBasis
EDB authorisationThe scheme advertised (PDS, IRS, RES, Smart City, G+2) and proof that the programme falls under itEDB, notaryNon-Citizens (Property Restriction) Act; EDB guidelines
PermitThe Building and Land Use Permit or the Outline Planning Permission, with its number and dateSeller, notaryEDB guidelines, documents in the file
Completion guaranteeThe clause in the deed and, where it rests on the programme’s terms, proof held by the notaryNotaryCivil Code, arts 1601-7, 1601-31 to 1601-37
Selling companyIts exact name, registration, directors, annual filingsCompanies registerCompanies Act; register website
Developer registrationIts registration number with the Real Estate Agent AuthoritySeller, REAAReal Estate Agent Authority Act 2020; official page
Past deliveriesProgrammes already handed over, with announced and actual datesVisit, buyersPractical, to be documented yourself

The first three are decisive

Without authorisation, permit or guarantee, there is no file. The next three gauge how serious the operation, and the party behind it, really are.

Ask for everything in writing

A spoken answer is worth nothing on the day of a dispute. Ask for each document by email and keep the replies with your contract.

Westimmo carries out these checks for you

Before presenting a programme, our team gathers the documents in the file and hands them to you. You decide knowing the facts.

03 Approval and permit

EDB approval and building permit

For a foreign buyer, the EDB authorisation is a condition of the purchase. The permit is a condition of the building work.

  1. The EDB authorisation. Any acquisition by a non-citizen under IRS, RES, PDS, Invest Hotel, Smart City or G+2 requires EDB authorisation, approved by the minister. It is valid for six months.
  2. The programme already approved. For a new property bought directly from the developer under IHS, PDS or Smart City, the selling company already holds the programme certificate: the buyer does not file an individual certificate. That does not remove the need to check: the EDB examines the project beforehand, and you check that the programme is the one you are being sold.
  3. The permit. For an off-plan sale, the file submitted to the EDB includes the Building and Land Use Permit or the Outline Planning Permission. Ask for its number and date, and check that they match the address and the number of units advertised.
  4. The guarantee letter. The EDB guidelines require, for any off-plan sale, a letter from a financial institution confirming a financial completion guarantee. The seller should therefore be able to show it to you or set out its terms.
  5. The buyer’s file. A non-citizen buyer’s file includes in particular the sale agreement endorsed by a notary, a bank letter confirming financial standing and a certificate of character less than six months old. The file fee is Rs 25 000, non-refundable.
  6. The scheme displayed. Each programme page on our site states the scheme. Compare it with what the contract says: an advertised scheme and a written scheme that differ are grounds for stopping immediately.

Authorised is not delivered

Approval opens the sale to a non-citizen. It says nothing about how far the building work has advanced or about the seller’s financial strength: those are other checks.

Exchange control rules

For a first sale under an approved scheme, 85% of the price is paid in rupees to the developer. The details are in our guide to buying as a foreigner.

04 The companies register

The company’s accounts at the register

The companies register (CBRD) lets you find out which company is actually selling.

Companies register →

The seller’s exact name

The reservation contract names a company. Note its exact name and look it up on the register’s portal: the online search is free. A property operation is often carried by a dedicated company, separate from the brand you know.

Directors and legal form

The register shows the company’s legal form, its date of incorporation and its directors. A company set up shortly before the sale is not suspect in itself: it is the usual set-up for an operation. It simply raises one question: who guarantees completion?

Annual filings

The register’s website offers filing of the annual return and requests for documents. Ask the register what it can issue on the company concerned.

Same name everywhere

The company’s name on the contract, on the EDB certificate and on the operation’s bank account must be the same. Any difference should be explained in writing before any payment.

An additional registration

Since the 2020 Act, the Real Estate Agent Authority also registers land promoters and property developers: phase 1 of registration began on 1 August 2026. Ask for the seller’s registration number.

A seller subject to due diligence

Property developers fall within the scope of the anti-money laundering law (FIAMLA). Expect to be asked where your funds come from: it is a legal obligation, not a commercial formality.

05 Delivery record

What a past delivery reveals

Promises are read in a brochure; reliability is observed on a programme already handed over.

  1. List the programmes already handed over. Ask the seller for its delivered programmes, with the launch date, the delivery date announced in the deed and the date the keys were handed over. The gap between the two dates is the most telling indicator.
  2. Visit an occupied programme. Nothing replaces a visit: common areas, finishes, visible leaks, the state of the green spaces. A programme delivered a year or two ago shows what becomes of the quality advertised.
  3. Talk to buyers. A managing agent or a resident will tell you more than a brochure: how quickly snagging items were cleared, service charges announced and actual, the relationship with the seller after handover.

A finding, never a verdict

A delay can have many causes. We publish no ranking of developers: the method lets you build the file yourself and compare real gaps.

Delay is settled in the deed

The Civil Code requires a delivery deadline in the deed of sale but sets no penalty for a late developer: have one written in next to the deadline (art. 1601-7, arts 1610 and 1611).

The ten-year guarantee follows the property

The seller is liable for hidden defects for ten years from acceptance of the works (arts 1646-1 and 1792). The quality of a programme should therefore also be checked after delivery.

06 The reservation contract

Reading a reservation contract

The preliminary contract is handed over before any payment. It sets what you can claim afterwards.

The off-plan buying guide →
Mauritian Civil Code, arts 1601-7, 1601-8, 1601-11, 1601-12, 1601-38 to 1601-45, read on 22 September 2026 and re-read on 9 November 2026.
ClauseWhat the law expectsWhat you checkText
Description of the propertySurface area, rooms, technical note, forecast price, planned date of saleThat the unit matches the plan and the specification of fittingsArts 1601-38 to 1601-43
Reservation depositPlaced in a special account in your name, at a bank or with a notaryThe account holder’s name, never an account of the sellerArts 1601-38 to 1601-43
No other paymentThe seller may neither demand nor accept any payment before the deedThat no “supplement” is requested before the deedArt. 1601-8
Cases for refundDeposit refunded in full in five cases, by registered letter, within three monthsThat the contract does not restrict these casesArt. 1601-45
Completion guaranteeMandatory mention in the off-plan deed of sale, on pain of nullityThe clause, the guarantor and the supporting documents held by the notaryArt. 1601-7(d) and arts 1601-31 to 1601-37
Delivery deadlineProvided for in the deedA precise date, and the consequences of a delay written into the contractArt. 1601-7(c); delay: arts 1610 and 1611
Termination indemnityCapped at 10% of the price; any contrary clause is deemed unwrittenThe amount of the fixed indemnityArts 1601-11 and 1601-12
Draft deedNotified at least one month before signingThat the reading period is respectedArt. 1601-44

The deposit is not an advance

The reservation deposit stays blocked until the deed. If it is requested in another account, or as a payment, stop.

The details are in the off-plan buying guide

Deposit caps, stage payments, remedies in case of delay and handover of the keys are detailed in our off-plan buying guide. This page does not repeat them.

07 Warning signs

The warning signs

No single sign condemns a programme on its own. Several together justify stepping back.

You are asked to pay before the deed

Apart from the reservation deposit in a special account, the law forbids the seller to demand or accept a payment before the deed (art. 1601-8).

The contract mentions no completion guarantee

The off-plan deed of sale must provide for it, on pain of nullity (art. 1601-7). A document that ignores it does not protect the buyer.

The seller cannot produce the permit

A missing permit number, a date that cannot be found or an address different from the programme advertised stops the file.

The seller’s name changes from one document to another

A different company on the contract, the invoice and the bank account: ask for a written explanation and proof of the link between them.

Manufactured urgency

“Last unit at this price”, “offer expires tomorrow”: a serious programme can withstand a week of checking.

A building site at a standstill

A site visit is possible. A site halted without explanation, or one that has not progressed since the last stage payment, calls for precise questions and a written answer.

A registration that cannot be found

A seller who cannot give its REAA registration number, when phase 1 has been open since 1 August 2026, owes you an explanation.

A price far below the market

A marked gap with comparable programmes in the same area is not a bargain until it is explained by the scheme, the land or the stage of construction.

08 The programmes

The catalogue programmes, by coast

We present programmes, not brands: each page states its scheme, its documents and its terms of sale.

All new programmes →

Prices are on the programme pages

Prices, availability and delivery dates change: see the page of each programme, kept up to date by our team, rather than a figure frozen in a guide.

Apply the same method to each one

Scheme advertised, permit, guarantee, selling company, delivered programme to visit: the six checks apply to every programme, whichever the coast.

11 Sources & methodology

Reliable, up-to-date information

The rules come from the official texts and the authorities’ pages, read on the dates indicated.

WestimmoProgramme pagesAGOOfficial legal textsEDBEconomic Development BoardREAAReal Estate Agent Authority
  • Mauritian Civil Code, arts 1601-1 to 1601-45, 1610, 1611, 1646-1 and 1792 — Attorney General’s Office
  • Non-Citizens (Property Restriction) Act, s. 3 — Attorney General’s Office
  • Economic Development Board — guidelines for the acquisition of residential property by non-citizens, IRS, RES, PDS and FAQ of February 2025
  • Real Estate Agent Authority Act 2020, s. 16, and official page reaamauritius.org, read on 9 November 2026
  • Financial Intelligence and Anti-Money Laundering Act 2002, First Schedule — FIU Mauritius
  • Companies register, companies.govmu.org, page read on 9 November 2026
  • Programme pages of real-estate-mauritius.mu, read on 9 November 2026

Texts read from 17 September to 9 November 2026. This guide does not replace a notary’s advice: have your file checked before you sign.

12 Frequently asked questions

Your questions about developers

Short answers, backed by the legal texts.

Frequently asked questions on checking a developer in Mauritius